Indiana Crossroads Wind FarmReynolds, Indiana

300MW Wind Farm

Project Overview

Sargent Electric was the electrical contractor for this 300MW Wind Farm completing the tower wiring of 72, 4.2MW Vestas Wind Turbines and the construction of the 3.7-mile 345kV Transmission Line. Sargent, together with White Construction, completed the project (4) weeks early.

Project Details

 

Owner:

EDP Renewables

General Contractor:

White Construction

Size:

300MW

Completion Date:

November 2021