Project Overview
Every season, Opening Day for the Pittsburgh Pirates attracts nearly 40,000 ticket holders to PNC Park. Sargent Electric Company’s challenge was to enhance the Park’s wireless coverage while ensuring that materials and equipment blended into the surroundings.
This project sounds like an easy task until unforeseen schedule changes arise. Our team was given just three work days for a project that would typically require 10 days to complete.
Project Details
- Twenty-six Hundred Feet of Fiber Optic Cable
- Three Bi-pole Antennas
- Three Radio Cabinents
- Power
- Grounding
- RF Cables